|
Lean pays off for F-15
support
for
F-15 work crews at Robins AFB
By
Gene Rector
Telegraph
Staff Writer
ROBINS AIR FORCE BASE
-
Officials at Robins usually agree with the adage: Don't try
to fix something if it's not broken. But they made an exception
with the F-15 maintenance line in January of this year - an
exception that proved to be painful before it became beneficial.
They undertook the change because the massive overhaul of the
nation's premier air superiority fighter aircraft had reached
a stubborn benchmark. "We were about as good as we could
get using current methods," said Ellen Griffith, who oversees
the process for the
Warner Robins Air Logistics Center.
Each of the Air Force's more than 700 F-15s must receive complex
and extensive overhaul every six years. About 100 aircraft from
bases around the world undergo the treatment each year at Robins.
It begins with de-arming, de-fueling and de-painting, then proceeds
through wing removal, a host of tests, checks and repairs and
installation of new or modified components. The process concludes
with reattachment of wings, refueling, a functional test flight
and repainting. If everything goes according to plan, the jet
goes home after about 114 days.
But there were always hiccups and unpredictables with the old
system. Due dates - the date promised for completion of the
process - weren't always met. "So we decided to go to Lean
about a year ago because we thought that was the only way we
would get dramatic improvements,"
Griffith said.
The reason was simple: The war on terrorism was heating up and
combat units needed their airplanes overhauled and returned
on time.
Lean is an initiative pioneered by Japanese manufacturer
Toyota to streamline processes and cut waste. It had been applied
successfully to a number of areas at Robins, but not to an entire
depot maintenance line. And, predictably, there was a learning
curve.
The goal was a continuous, one-piece flow with aircraft moving
through the overhaul line - 18 different stops - at a specified
rate.
"Moving a jet every few days from one repair station to
the next means everything's got to be in place," said
Griffith. "If we came to a work stoppage under the old
system, we would put the work crew on another jet until we were
supportable
again. Then we put the crew back on the original aircraft, hurried
up, worked overtime and got things caught up. But with one-piece
flow, you can't do that."
Wartime demands made it even more challenging. Combat units
had priority for spare parts. Wings had to be repaired not only
for the Robins maintenance line but for direct use in the field.
Key mechanics were sent overseas to solve technical problems.
The darkest hours came in June and July when due dates began
to tank and up to 50 F-15s crowded the Robins parking ramp.
"Our ideal number of aircraft on base is 32," said
Griffith. "We were bottlenecked, backed up and couldn't
have picked a worse time to do the conversion to Lean. As my
boss said, we drained the swamp so all the stumps stuck up.
And we spent most of the year addressing those stumps."
The naysayers had a field day, claiming the change was counterproductive.
"I had people tell me it would take a year to work the
ramp population down," admitted
Griffith.
But Lean principles began to kick in. "Lean forces you
to have all the
support
stuff where and when you need it," she said. "That
includes all the parts, tools, technical data, maintenance stands
in each specific work cell. It makes it really efficient for
the mechanic."
The effects were obvious by late September. "We developed
a recovery plan, everybody worked so hard and we got the ramp
population down to our goal,"
Griffith
said. "Now, we have 31 jets on station so we've made an
awful lot of progress in the last 4-5 months."
Most companies take 3-4 years to fully implement Lean. "But
the Air Force isn't a terribly patient organization," she
said. "There's been a lot of pressure on us to be successful
quickly and we've done that."
Most important,
Griffith believes Lean has won the hearts and minds of the workers
- the mechanics and technicians actually doing the overhauls.
"Even our crustiest supervisors now say this is the right
way to do business and they would not like to go back to the
way we did it before," she said. "We still have a
few naysayers,
but the large majority of our folks see the benefits."
That's because the worker becomes part of the solution under
Lean. "This is a great opportunity for the mechanic to
be heard,"
Griffith said. "They're the ones who really know how the
job should be done. We take their feedback and we act on every
one."
She said some of 2003's most gratifying moments have come at
training sessions. "Some of our mechanics have shut down
the Lean naysayers by saying, 'Management is finally listening
to us.' "
Griffith
doesn't claim that all the problems are solved. Robins is scheduled
to overhaul 104 F-15s in 2004 and hopes to meet a due date schedule
of 114 days per aircraft. Anything can happen.
"We're making a lot of progress in getting everything in
place. We've topped the learning curve," she said. "But
I always cringe when my boss says we've rounded the corner,
because you never know what's around that next corner."
To contact Gene Rector, call 923-3109, extension 239, or e-mail
grector@macontel.com.
|